THE MAKING ROOMS, BLACKBURN
CM OXENDALE Ltd partnered with CAREFOOT PLC at tender stage to provide costs and a full design proposal for the new ‘MAKING ROOMS’ project in blackburn.The works included stripping out existing redundant systems, installation of new Gas fired boiler plant and hot water calorifer. Gas interlock systems.Ventilation to the main work area had to be carefully designed to created a comfortable work environment, with supply air into the café area, extracting within the work space. Attenuation installed to the transfer ducts prevent the Sediment traps were installed to key locations within the pottery making areas to ensure blockages didn’t occur in drainageA spray booth has been installed to the 2nd floor for the use by patrons, this includes for interlocked extract and supply AHU systems, given the tight town centre location, the AHU had to be delivered in small sections, take up stairs and positioned on the roof.